Pembroke Power Station 400 kV

Laying of 8.8 km of 420 kV cable for the UK’s largest combined cycle gas turbine power plant

Location:
Pembroke, UK

Operator:
RWE npower

Scope of deliverables provided by BRUGG:

  • 8.8 km 400 kV XLPE cable 1 x 1000 mm²
  • 30 x 420 kV open-air sealing ends
  • Supervision of cable routing
  • Sealing end assembly, resonance testing by KEMA

Contact

Phone
+41 56 201 37 77