Brugg Cables supports the energy transition in Germany

The generation of renewable energies, particularly in the north of Germany, as well as the necessary expansion of the electricity grids, is actively supported by Brugg Cables as a general contractor for cable projects.

The project scope for the customer Schleswig-Holstein Netz AG (SHN) consisted of the cable connection between two substations with a total capacity of 600 MVA, which Brugg Cables planned via three 110 kV double cable systems.

Brugg Cables stands for the successful project management of high-voltage cable projects in Germany. Our own team with decades of experience in the realisation of complex cable projects from 110 kV, project planning by our cable engineers and our high-voltage fitters for the accessories - all this contributes to the success of the project.

Learn more about the Brugg Cables cable projects